The process of stakeholder consultations began on November 20th 2013 and will continue throughout the project. Meetings held to date as follows:
20 November 2013 |
Malabar |
Ministry of Works and Infrastructure |
10 December 2013 |
Malabar |
HDC, Ministry of Housing and Land and Marine Affairs |
10 December 2013 |
Malabar |
WASA, T&TEC, TSTT, FLOW, Ministry of Works and Infrastructure Highway Division, Regional Corporations, Ministry of Environment and Water Resources Drainage Division and NGC |
06 August 2014 |
Malabar |
WASA Operations Department |
19 August 2014 |
Malabar |
Malabar Community |
21 August 2014 |
La Horquetta |
La Horquetta Community |
03 February 2015 |
Malabar |
WASA Operations Department |
07 April 2015 |
Malabar |
Tunapuna/Piarco Regional Corporation |
09 April 2015 |
Malabar |
Arima Borough Corporation |